ORU Banner SaaS Modernization
Composition of the Remaining 18% - Root Causes, Action Plan & Key Attention Items
82%
Overall Complete
Oct 12
Go-Live Date
108 days
Time Remaining
72 days
Buisiness Days Remaining
18%
Work Remaining
--%
Integrations Complete
--%
Reports Complete
--%
Forms Complete
1
Workstream Breakdown
Contribution to Remaining --%.
Each row below shows one workstream: its completion rate, its estimated weight in the overall project, and its calculated contribution to the remaining --%.
| Area | Weight | Completion | Remaining | Contribution | Key Facts |
|---|---|---|---|---|---|
|
Value Stream & Capabilities
Student, HR, Finance, T&L (86% done)
|
33% | 86% | 14% | ~4.6% | Teaching & Learning 86% · HR 88% · Finance 82% |
|
Reports
498 total - 444 done - 54 remaining
|
11% | 89% | 11% | ~2.2% | 498 go-live required · 444 done · 54 remaining |
|
Platform & Products
ISE, EUP, Evisions, Experience Cards (88% done)
|
12% | 88% | 12% | ~1.6% | ISE 99% · EUP 100% · Evisions complete |
|
Data Migration
Mock cycles, validation (73% done)
|
9% | 73% | 27% | ~2.3% | Mock 4 complete (Jun 17). Mock 5: Aug 10-21. |
|
Integrations
42 total - 35 done - 7 remaining (83% done)
|
7% | 83% | 17% | ~1.3% | 42 required for go-live · 35 complete · 7 remain |
|
Cutover & Deploy Phases
Cutover, Business Simulation, Staging, Deploy (58% done)
|
14% | 58% | 42% | ~5.9% | Cutover planning and deployment preparation are progressing toward go-live. |
|
Complete Phases
Prepare, Plan, SAE, Environment, iPass, Extensibilities
|
5% | 100% | 0% | - | Prepare, Plan, SAE, Environment Readiness, iPass, Extensibilities - all 100% |
| TOTAL PROJECT | 100% | 82% | 18% | ~18% | 4.6% + 2.2% + 1.6% + 2.3% + 1.3% + 5.9% = ~ 18% |