ORU Banner SaaS Modernization
Composition of the Remaining 20% - Root Causes, Action Plan & Key Attention Items
81%
Overall Complete
Oct 12
Go-Live Date
108 days
Time Remaining
72 days
Buisiness Days Remaining
19%
Work Remaining
--%
Integrations Complete
--%
Reports Complete
--%
Forms Complete
1
Workstream Breakdown
Contribution to Remaining 20%
Each row below shows one workstream: its completion rate, its estimated weight in the overall project, and its calculated contribution to the remaining 20%.
| Area | Weight | Completion | Remaining | Contribution | Key Facts |
|---|---|---|---|---|---|
|
Value Stream & Capabilities
Student, HR, Finance, T&L (86% done)
|
33% | 86% | 14% | +4.6% | Teaching & Learning 86% · HR 86% · Finance 82% |
|
Reports
498 total - 427 done - 71 remaining
|
19% | 85% | 15% | +2.9% | 498 go-live required · 427 done · 71 remaining |
|
Platform & Products
ISE, EUP, Evisions, Experience Cards (88% done)
|
13% | 88% | 12% | +1.6% | ISE 99% · EUP 100% · Evisions complete |
|
Data Migration
Mock cycles, validation (70% done)
|
9% | 70% | 30% | +2.7% | Mock 4 complete (Jun 17). Mock 5: Aug 10-21. |
|
Integrations
42 total - 32 done - 10 remaining (76% done)
|
7% | 76% | 24% | +1.7% | 42 required for go-live · 32 complete · 10 remain |
|
Cutover & Deploy Phases
Cutover, Business Simulation, Staging, Deploy (32% done)
|
14% | 32% | 68% | +9.5% | Largest single contributor - expected at this project stage. Cutover plan begins Aug-Sep. |
|
Complete Phases
Prepare, Plan, SAE, Environment, iPass, Extensibilities
|
5% | 100% | 0% | - | Prepare, Plan, SAE, Environment Readiness, iPass, Extensibilities - all 100% |
| TOTAL PROJECT | 100% | 79.9% | 20.1% | = 20.1% | +4.6% + +2.9% + +1.6% + +2.7% + +1.7% + +9.5% = 20.1% |